What contingency factors might the planning Habitat executives have to do for the wise use of his gift? How might those contingency affect the panning?"
第1题
Contingency planning should include all but which of the following?
A The development of a contingency allowance determined by combining (layering) various estimate segments to form. larger estimate segments.
B the development of schedule alternatives and work-around
C the management of a contingency budget
D an assessment of project shut-down liabilities.
E A and C
第3题
A.Resource leveling.
B.Manpower leveling.
C.Resource limited planning.
D.Manpower planning.
E.Manpower contingency planning.
第4题
A.The location of the organization
B.The size of the organization
C.One’s position and level in the organizational hierarchy
D.Level in hierarchy
E.Importance of an activity
第5题
Response Planning is the responsibility of the functional areas and considers
A mitigation.
B deflection.
C contingency planning.
D unforeseen occurrences.
E All of the above.
第6题
Risks that cannot be identified or evaluated _____ .
A should be deflected to the contracting officer.
B should be handled via contingency allowances.
C should be ignored, since they cannot be identified.
D should be ignored, since they are not covered in the Risk Assessment.
E C and D
第7题
Which of the following is referred to as sunk cost:
A . management reserve
B . contingency fund
C . cost budgeted for construction under water
D . expended funds over which there is no further control
E . forecasted budget over-runs
第8题
Managerial Reserves are:
A.allowances to account for price changes that can occur over the life of a project.
B.incentive fees paid to managers for good performance.
C.funds used to offset poor cost or schedule estimates.
D.accounts to allocate and maintain funds for contingency programs
E.All of the above.
第9题
A.Slack for each activity, critical path.
B.Slack for each activity, high risk activities.
C.Manpower shortages, high risk activities.
D.High risk activities, non-critical paths.
E.Manpower availability, contingency plans.
第10题
34 Planning activities such that predetermined resource availability pools are not exceeded is called: A. Resource leveling.
B. Manpower leveling.
C. Resource limited planning.
D. Manpower planning.
E. Manpower contingency planning