[主观题]

59By using Project Risk Management techniques, project managers can develop strategies tha

59 By using Project Risk Management techniques, project managers can develop strategies that do all but which of the following:

A. Significantly reduce project risks

B. eliminate project risks

C. provide a rational basis for better decision making

D. identify risks, their impact(s), and any appropriate responses

E. None of the above

答案
查看答案
更多“59By using Project Risk Management techniques, project managers can develop strategies tha”相关的问题

第1题

R & D project managers in high-tech companies most often motivate using _____ power.AE

R & D project managers in high-tech companies most often motivate using _____ power.

A Expert

B Reward

C Referent

D Identification

E None of the above

点击查看答案

第2题

46R & D project managers in high-tech companies most often motivate using _____ power.

46 R & D project managers in high-tech companies most often motivate using _____ power.

A. Expert

B. Reward

C. Referent

D. Identification

E. None of the above

点击查看答案

第3题

Using the data shown in the Special window, Activities P, Q, and T are critical path activ
ities. In order to shorten the time duration of the project, which activity should be "crashed" first?

A . P

B . Q

C . R

D . S

E . T

点击查看答案

第4题

A project manager can exchange information with the project team using which media?Atactil

A project manager can exchange information with the project team using which media?

A tactile

B audio

C olfactory

D visual

E All of the above.

点击查看答案

第5题

Which of the following factors has historically been the greatest contributor to project f
ailure?

A.Planning performed by a planning group.

B.Poor financial estimates.

C.Lack of sufficient management reserve.

D.Lack of management support.

E.Not using an automated tracking tool.

点击查看答案

第6题

By using Project Risk Management techniques, project managers can develop strategies that
do all but which of the following:

A Significantly reduce project risks

B eliminate project risks

C provide a rational basis for better decision making

D identify risks, their impact(s), and any appropriate responses

E None of the above.

点击查看答案

第7题

Using the figure in the Special Window, what is the probability of success for Project B?A

Using the figure in the Special Window, what is the probability of success for Project B?

A 0.3

B 0.2

C 0.35

D 0.15

E 0.12

点击查看答案

第8题

Using the figure in the Special window, By how many weeks can activity "F" slip without ex
tending the end date of the project?

A . 0

B . 1

C . 2

D . 3

E . 4

点击查看答案

第9题

Using the scenario in the special window, the project manager:Awill probably spend the wee

Using the scenario in the special window, the project manager:

A will probably spend the weekend reviewing the data.

B Won't ask for the report again.

C Has a preference for written communication.

D Has chosen an inappropriate medium.

E Is experiencing communication overload.

点击查看答案

第10题

Using the scenario in the special window, the project manager appears to be a _____ manage
r.

A . 1, 9

B . 9, 1

C . 1, 1

D . 9, 9

E . 5, 5

点击查看答案
下载APP
关注公众号
TOP
重置密码
账号:
旧密码:
新密码:
确认密码:
确认修改
购买搜题卡查看答案 购买前请仔细阅读《购买须知》
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《服务协议》《购买须知》
立即支付 系统将自动为您注册账号
已付款,但不能查看答案,请点这里登录即可>>>
请使用微信扫码支付(元)

订单号:

遇到问题请联系在线客服

请不要关闭本页面,支付完成后请点击【支付完成】按钮
遇到问题请联系在线客服
恭喜您,购买搜题卡成功 系统为您生成的账号密码如下:
重要提示:请勿将账号共享给其他人使用,违者账号将被封禁。
发送账号到微信 保存账号查看答案
怕账号密码记不住?建议关注微信公众号绑定微信,开通微信扫码登录功能
请用微信扫码测试
优题宝