[主观题]

Network schedules are prepared during the _____ phase and updated during the _____ phase.A

Network schedules are prepared during the _____ phase and updated during the _____ phase.

A.Conceptual, execution.

B.Development, implementation.

C.Development, close-out.

D.Implementation, close-out.

E.Planning, finishing.

答案
查看答案
更多“Network schedules are prepared during the _____ phase and updated during the _____ phase.A”相关的问题

第1题

Flextime and compressed workweeks are two popular alternative work schedules used by emplo
yers to improve the quality of work life of their employers. Which of the following statements concerning these alternative work schedules is not true?

A . Flextime schedules alter the employee's working hours but not the number of hours worked each day

B . Both flextime and compressed workweek schedules make scheduling more complex for the employer

C . Both flextime and compressed workweek schedules can complicate compliance with overtime regulations

D . Fatigue is a disadvantage of compressed workweek schedules because employees must work longer than the traditional eight hour work day

E . Under flextime schedules, the working hours are established by the employer

点击查看答案

第2题

The utility of network-based schedules:A.Reveals interdependencies.B.Facilitates "what if"

The utility of network-based schedules:

A.Reveals interdependencies.

B.Facilitates "what if" exercises.

C.Highlights critical activities.

D.Provides information on resource requirements, time requirements and tradeoffs.

E.All of the above.

点击查看答案

第3题

107The utility of network-based schedules: A.Reveals interdependencies. B.Facilitates "wha

107 The utility of network-based schedules:

A. Reveals interdependencies.

B. Facilitates "what if" exercises.

C. Highlights critical activities.

D. Provides information on resource requirements, time requirements and tradeoffs.

E. All of the above

点击查看答案

第4题

The most common types of schedules are Gantt charts, milestone charts, line of balance, an
d:

A.Networks.

B.Time phased events.

C.Calendar integrated activities.

D.A and C only.

E.B and C only.

点击查看答案

第5题

Each workday, the workers followed the same schedules and rarely ________ from this
routine.

A) deviated

B) disconnected

C) detached

D) distorted

点击查看答案

第6题

Upon completion of 75% of the project, the original schedules and cost estimates that were
submitted at the inception of the project are referred to as the:

A . Baseline costs

B . Budgeted costs.

C . Estimates upon completion costs

D . Scheduled costs

E . None of the above

点击查看答案

第7题

93The most common types of schedules are Gantt charts, milestone charts, line of balance,

93 The most common types of schedules are Gantt charts, milestone charts, line of balance, and: A. Networks.

B. Time phased events.

C. Calendar integrated activities.

D. A and C only.

E. B and C only.

点击查看答案

第8题

(c) Explanatory notes, together with relevant supporting calculations, in connection with

(c) Explanatory notes, together with relevant supporting calculations, in connection with the loan. (8 marks)

Additional marks will be awarded for the appropriateness of the format and presentation of the schedules, the

effectiveness with which the information is communicated and the extent to which the schedules are structured in

a logical manner. (3 marks)

Notes: – you should assume that the tax rates and allowances for the tax year 2006/07 and for the financial year

to 31 March 2007 apply throughout the question.

– you should ignore value added tax (VAT).

点击查看答案

第9题

197Proper implementation of project management will guarantee that: A.Budgets will be met.

197 Proper implementation of project management will guarantee that:

A. Budgets will be met.

B. Schedules will be adhered to. "

C. Quality/performance will be met.

D. The project will be a success.

E. None of the above

点击查看答案

第10题

The reason that cost management is so difficult in project management is that:A.Projects b

The reason that cost management is so difficult in project management is that:

A . Projects by definition and nature are non-recurring events and are therefore difficult to predict.

B . There are no tools for identifying project tasks.

C . Project managers do not care about tracking costs, as only schedules are important to all project managers.

D . A and B only

E . B and C only

点击查看答案
下载APP
关注公众号
TOP
重置密码
账号:
旧密码:
新密码:
确认密码:
确认修改
购买搜题卡查看答案 购买前请仔细阅读《购买须知》
请选择支付方式
  • 微信支付
  • 支付宝支付
点击支付即表示同意并接受了《服务协议》《购买须知》
立即支付 系统将自动为您注册账号
已付款,但不能查看答案,请点这里登录即可>>>
请使用微信扫码支付(元)

订单号:

遇到问题请联系在线客服

请不要关闭本页面,支付完成后请点击【支付完成】按钮
遇到问题请联系在线客服
恭喜您,购买搜题卡成功 系统为您生成的账号密码如下:
重要提示:请勿将账号共享给其他人使用,违者账号将被封禁。
发送账号到微信 保存账号查看答案
怕账号密码记不住?建议关注微信公众号绑定微信,开通微信扫码登录功能
请用微信扫码测试
优题宝